Profile Park

Profile Park Elliott Group
  • Client
    Centrica (GIL)
  • Value
    €15,000,000

Our Project

Elliott Group delivered all Civil, Structural, and Architectural (CSA) works for the construction of a 100MW gas-fired power plant, including all balance-of-plant infrastructure, equipment, and buildings. The development comprised an Engine Hall Building with 5 gas engines, an Electrical Annex, Workshop, Tank Farm, Security Hut, Gas AGI with kiosk, Radiator Coolers, 2 electrical transformers, and an Exhaust Stack.

The works also included fuel and process storage systems—for diesel oil, SCR urea, lube oil, fire water, and effluent collection—along with underground attenuation and drainage networks, access roads, parking, footpaths, landscaping, and fencing.

As CSA Specialist Package Contractor (SPC), Elliott Group undertook full Design & Build responsibilities, including Contractor Design Portions (CDP) for rebar detailing, temporary works, and technical submissions. Working alongside GCIL, the Project Management Consultancy, all CSA packages were delivered on time, to the highest safety and quality standards.

Key Features

• 100MW gas-fired power generation facility
• Engine Hall with 5 gas fired recipricating internal combustion engines (RICE) and 5no. 27m stacks
• Electrical Annex and 110kV Substation & Control Building
• Gas AGI with Instrument House
• Comprehensive Tank Farm for diesel, oil, urea & water systems
• Radiator cooling and ventilation units


View more Mission Critical

  • Start Date
    April 2023
  • End Date
    June 2024
  • Duration
    69 weeks
  • Architect
    Yoksel Proje

Project Gallery

Get in touch

At Elliott Group, we are proud of our exceptional team of professionals who are available to talk to you in person or who can answer any question you might have.

  • Start Date
    April 2023
  • End Date
    June 2024
  • Duration
    69 weeks
  • Architect
    Yoksel Proje