  • Client
    Dairygold
  • Location
    Cork
  • Value
    €6,000,000

Dairygold awarded Elliott Group, the upgrade and expansion of its existing milk processing facility at Castlefarm Site, Mitchelstown, County Cork, comprising of:

  • The construction of a wet process building comprising of two floors, an electrical room and relevant tank based area
  • Construction of a dryer building comprising of 3 floors, an electrical room, an MCC room and all associated civil and structural works.

The project is a mixture of Demolition works, the construction of RC Frame, and also a structural steel frame with Infill panels. The project is executed within a live manufacturing facility.

 

The project is broken into 2 Phases.

  • Phase 1 (Wet Process) Extensive Demolition works followed by the construction of an RC Frame building, Rennet tank bund and associated tank plinths.
  • Phase 2 (Dry Process) Extensive Demolition works followed by the construction of a Structural Steel Frame, with RC Slabs, precast stairs, blockwork infill panels, new control rooms and changing rooms.
  • Building Type
    Food Production
  • Scale
    2200m2
  • Duration
    12 months
  • Client
    Dairygold
  • Services Engineer
    OLS

Project Gallery

Get in touch

At Elliott Group, we are proud of our exceptional team of professionals who are available to talk to you in person or who can answer any question you might have.

  • Builing Type
    Food Production
  • Scale
    2200m2
  • Duration
    12 months
  • Client
    Dairygold
  • Services Engineer
    OLS