Goswell Road Chiller Replacement

  • Client
    Goswell Road Chiller Replacement
  • Location
    39 Moreland Street, London
  • Value
    €4,560,000

Project Overview

The Goswell Road Chiller Replacement project comprises the phased replacement of 13 rooftop air cooled chillers serving a live mission critical data centre in central London. The works include the decommissioning and removal of existing plant, installation of new high efficiency chillers and acoustic enclosures, structural alterations, mechanical and electrical upgrades, BMS integration, commissioning, and associated lift operations.

Delivered within a fully operational data centre environment, the project is being undertaken in two carefully managed phases to maintain uninterrupted cooling resilience and operational continuity throughout the works. Extensive planning, off site prefabrication, weekend crane operations, temporary cooling provision, and integrated commissioning strategies are employed to minimise risk and ensure seamless project delivery.

Key Features

• 13 No. rooftop chiller replacements
• Live operational data centre environment
• Phased delivery maintaining cooling resilience
• Weekend crane lifting operations
• Temporary cooling installation
• Mechanical, electrical and structural upgrades
• BMS and Octapipe integration
• Acoustic enclosures and noise mitigation
• Off-site prefabrication solution
• Commissioning and integrated systems testing.

  • Start Date
    June 2026
  • End Date
    March 2027
  • Duration
    45 weeks
  • Client
    Stellanor
  • Services Engineer
    CJK Engineering

Get in touch

At Elliott Group, we are proud of our exceptional team of professionals who are available to talk to you in person or who can answer any question you might have.

  • Start Date
    June 2026
  • End Date
    March 2027
  • Duration
    45 weeks
  • Client
    Stellanor
  • Services Engineer
    CJK Engineering